Print Back to Calendar Return
 
6.
         
BRENTWOOD PLANNING COMMISSION
Meeting Date: 09/04/2018  

Information
PROJECT NUMBER
BPC1808-015        
 
PROJECT DESCRIPTION
Revised Site Plan -  Brentwood High School, Soccer Dugout improvements

SBR Construction, LLC request approval to replace the existing soccer dugouts at the Brentwood High School.  The new dugouts will be in the same locations.  The dugouts measure approximately 7 feet wide by 28 feet long They will be faced with brick to match the main building and have blue metal standing seam roofs. 
 
The existing dugouts are constructed of pressure treated lumber and siding and are in need of replacement. 
 
The existing shrubbery at the rear of the dugouts will be removed as part of the construction. 
 
WCS has approved the proposed design.
 
ZONING OF PROPERTY
Zoning SI-2 
APPLICANT NAME/ADDRESS
Mr. Brent Thoeny, SBR Construction, LLC, 8216 Glover Drive, Brentwood, TN  37027 
Attachments
Final Staff Report
Plan Set
Proposal Details

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved