Approval of Recommended Roadway Repairs and Improvements List for FY2019
Submitted by: Todd Hoppenstedt, Public Works
Department: Public Works  

Information
Subject
Approval of the Recommended Roadway Repairs and Improvements list for FY 2019
Background
Attached is a list of City of Brentwood maintained streets recommended for repair and improvement in FY 2019.  The list was developed using data from a Commission-approved contract with Data Transfer Solutions (DTS) for a video assessment of all city road segments, which was conducted in the spring/summer of 2017.  In addition, staff physically evaluates the top priorities each year to further refine the list.  We consider condition, traffic type, traffic volume, current maintenance demands, and reports of pavement failures before preparing the recommended list.

The FY2019 budget for Roadway Repairs and Improvements is $2,300,000, comprised of $300,000 from the Capital Projects Fund, $760,000 from the General Fund, and $1,240,000 from the State Street Aid Fund.

The attached list of streets represents our highest priorities identified at this time.  As the work progresses through the year, staff will continually review actual project costs to determine what additional work can be added to the contract in order to optimize the use of available funds.

Staff recommends maintaining approximately a 14% contingency for emergency repairs or unforeseen pavement failures and potential fluctuations in the TDOT asphalt cost index during the course of the fiscal year.  Emergencies repairs could include pavement buckles from the heat or failures experienced throughout the winter months usually attributed to freeze and thaw cycles.  The contingency funds allow some flexibility in adjusting the plan to correct emergency pavement failures.  If the contingency is not used by the spring of 2019, we will proceed with repair of the next available street or streets from the priority list.

Please direct any questions to the Public Works Director.
Staff Recommendation
Staff recommends approval of the FY 2019 paving list.
Previous Commission Action
No previous Commission Action.

Fiscal Impact
Amount : $2,300,000
Source of Funds: See Table Below
Account Number: See Table Below
Fiscal Impact:
Fiscal Impact
Amount:                                                              $2,300,000
Source of Funds:                                               See table
Account Number:                                               See table
Fiscal Impact:

Funding for the $2.3 Million FY  2019 street paving program is provided in the adopted as follows:
Fund Account Amount
General Fund 110-43120-82640 $760,000
State Street Aid Fund 121-43120-82640 1,240,000
Capital Projects Fund 311-43100-1000 $300,000