Print Back to Calendar Return
  Consent  
3.
         
Brentwood City Commission Agenda
Meeting Date: 12/13/2021  
Resolution 2021-143 - Amendment to Agreement with American Constructors to Establish Final Guaranteed Maximum Price for Fire Station 5 Construction
Submitted by: Kirk Bednar, Administration
Department: Administration  

Information
Subject
Resolution 2021-143 - Amendment to Agreement with American Constructors to Establish Final Guaranteed Maximum Price for Fire Station 5 Construction.
Background
On August 23, 2021, the Board of Commissioners approved an amendment to the agreement with American Constructors to establish a Phase 1 Guaranteed Maximum Price (GMP) of $6,174,633 for construction of Fire Station 5.  At that time, it was noted that several subcontractor bid packages had to be rebid before a final GMP could be established.  However, it was estimated then that after the rebid of those packages the final GMP would be approximately $6,950,000.

Subsequent to that approval, American Constructors completed the rebidding process for the remaining subcontractor packages and an extensive value engineering process in consultation with the project design team and city staff.  As a result of this process, the attached amendment establishes the final GMP at $6,949,018.  This total still includes a $100,000 contingency allowance.  A breakdown of the various subcontractor bid package costs is included in the attached AIA Exhibit A.

The overall project budget for Fire Station 5 has not changed from what was originally presented in August:
 
 
Design $402,500
Materials Testing 32,000
Construction 6,950,000
Apparatus 845,000
Furniture, Technology, and Misc. 150,000
TOTAL $8,379,500

As discussed in August, funding currently available or programmed in the future for this project totals $7,575,000, leaving a project budget deficit of a little more than $800,000. At this time, staff would propose that the funding source to make up the project deficit be a General Fund FY 2022 year-end transfer of excess revenue of $805,000 to be completed as part of a FY 2022 year-end budget amendment.  Note that this amount would be in addition to an already planned transfer of $2,000,000 from projected FY 2022 excess revenues.  The overall funding budget for the project is attached for your review.

If you have any questions, please contact the City Manager.
Staff Recommendation
Staff recommends approval of Resolution 2021-143 establishing the final GMP for Fire Station 5.
Previous Commission Action
The Phase 1 GMP amendment was approved by the Board of Commissioners via Resolution 2021-99 on August 23, 2021.

The original construction management services agreement with American Constructors was approved by the Board of Commissioners via Resolution 2021-49 on April 26, 2021.
 
 

Fiscal Impact
Amount : $774,385
Source of Funds: Capital Projects Fund
Account Number: 311-45200-5018
Fiscal Impact:
This final GMP amendment increases the project GMP by $774,385 over the original Phase 1 GMP established in August 2021.

Funding currently available or programmed in the future for this project totals $7,575,000, leaving a project budget deficit of a little more than $800,000. At this time, staff would propose that the funding source to make up the project deficit be a General Fund FY 2022 year-end transfer of excess revenue of $805,000 to be completed as part of a FY 2022 year-end budget amendment.  Note that this amount would be in addition to an already planned transfer of $2,000,000 from projected FY 2022 excess revenues. 
Attachments
Resolution 2021-143
Amendment2 Establishing Final GMP_2021-054
Fire Station Funding Plan
Signed Resolution
Signed Amendment

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved