5.
         
Brentwood City Commission Agenda
Meeting Date: 11/09/2020  
Approval of Change Order to Agreement w/Sullivan Engineering for Design Services Related to Witherspoon/Raintree Forest Trail Connector
Submitted by: Todd Hoppenstedt, Public Works
Department: Public Works  

Information
Subject
Approval of change order to Agreement with Sullivan Engineering for Design Services Related to Witherspoon/Raintree Forest Trail Connector.
Background
In February 2020, the City Commission approved Resolution 2020-09 authorizing Sullivan Engineering, Inc. (SEI) to perform design services related to the Witherspoon/Raintree Forest Trail Connector.  The project has been designed, bid, and a contract awarded for construction.  However, the initial agreement with SEI did not include any Construction Administration or Observation Services as usually required on projects of this scale.

Staff requested a fee estimate from SEI for these additional services and requests the Commission's approval to add these additional services via a change order in the amount of $4,165.  It is staff's opinion these additional services are warranted and needed to ensure the work is completed in accordance with the design.

Please direct any questions to the Public Works Director.
Staff Recommendation
Staff recommends approval of this change order to increase the overall contract value to include Construction Administration and Observation Services.
Previous Commission Action
Resolution 2020-09 was approved on February 2020-09.
 

Fiscal Impact
Amount : $4,165.00
Source of Funds: Capital Projects Fund
Account Number: 311-43100-1001
Fiscal Impact:
Resolution 2020-09 was approved with a value of $55,102.75, which included a public meeting at $2,500 which was not held and therefore, not billed.  There was however an unanticipated TDEC Permit fee for work near the creek that added $500 to the billable amount.  Therefore, there is $2,000 worth of services remaining of the original contract.  The estimated cost to add Construction Administration and Observation services via this change order is $6,165.00 for a net overall increase of $4,165 to $59,267.75.
Attachments
SEI Construction Admin Proposal
Signed Change Order