Print Return
  Consent Agenda  
8.
         
BRENTWOOD PLANNING COMMISSION
Meeting Date: 01/03/2023  
Current Zoning: OSRD - OPEN SPACE RESIDENTIAL DEVELOPMENT

Information
Subject
BPC2209-006         Final Plat - Primm Farm Subdivision, Zoning OSRD - Applicant: Mr. Matt Bryant, M2 Group, LLC, P. O. Box 848, Franklin, TN 37065
General Information
M2 Group, LLC requests approval of a final plat that shows 24 lots on approximately 29 acres. The renovation work on the historic slave cabins must be completed and inspected for compliance before the plat will be signed for recording.  This plat reflects the recently revised preliminary plan changes to incorporate staggered side setbacks as allowed per the OSRD zoning.  
Conditions of Approval
Staff recommends that the following 2 conditions be attached to the approval of the request.
 
  1. The proposed renovation work on the historic slave cabins shall be completed and inspected for period correctness before the final plat for the project may be recorded. The inspection shall be performed by an architectural firm specializing in historic preservation and their fee paid by the applicant per Sec. 50-29(b) of the Brentwood Municipal Code.
     
  2. The Public Access Easement must be accepted by the City Commission before the plat will be signed for recording.  
Standard Requirements
Staff recommends that the following 11 conditions be attached to the approval of the request.
  1. Meter box lids are required to have thru hole to accommodate sensus smartpoint (520m) transceiver. If current lids cannot meet this requirement, oldcastle/carson 13x24 fiberlyte lid with sensus smartpoint 520m thru hole shall be used. 
     
  2. Prior to signing of plat, water and sewer as-builts (PDF & digital), CCTV inspection of gravity sewer mains (if applicable), and construction cost summary are to be provided to the Water Services Department. 
     
  3. Approval of a final plat by the Planning Commission shall become effective upon the date of the last signature required on the plat for recording. The initial vesting period shall be for a period of five years after approval.
     
  4. Add the following note to all pages of the final plat:
This final plat is subject to a vesting period, during which the development standards in effect on the date of approval will remain the standards applicable to this plan.  Upon expiration of the vesting period, development of the property shown on this plat may be subject to standards other than those that were applicable during the vesting period.  The vesting period for this plat expires on________________, unless extended by the City of Brentwood.  Persons relying on this plat after said date should contact the City of Brentwood to determine if development may continue as depicted on the plan. 
 
(Planning and Codes Department staff will insert the expiration year for the plat at the time the plat is ready for recording and may also make changes to the wording of the above note as necessary to carry out the intent of Standard Requirements 1, 2 and 3 below.)
  1. Provide the Planning staff with a digital copy of the proposed subdivision.  This request is consistent with Article 2.3 of the Brentwood Subdivision Regulations.  The file should be in AutoCAD .DWG or .DXF compatible format.  The file shall use the Tennessee State Plane coordinate system, FIPS Zone 4100, NAD 83 datum.  The digital copies must be received before the plat may be recorded.
     
  2. The property owner is responsible for all development fees including water and sewer service and tap fees, building permit fees and Public Works Project Fees.  The required fees shall be used for future infrastructure related improvements required by the proposed development. 
     
  3. A Storm Water System Long-Term Operation and Maintenance Plan for all storm water structures and facilities must be prepared, submitted and approved per Section 56-43 of the Brentwood Code.
     
  4. Complete building plans shall be submitted to the Planning and Codes Department for review, approval and issuance of the required permits before any work is begun. Additionally, all required electrical permits, issued by the State of Tennessee must be received before any work is begun.
     
  5. Development of this project shall comply with all applicable codes and ordinances of the City of Brentwood.
     
  6. Deviations from the approved plat in the development of the project or the failure to satisfy any standard requirements or special conditions of approval imposed by the planning commission will be considered a violation of the provisions of the Zoning Ordinance, which shall be subject to punishment as provided in Section 1-9 of the Brentwood Municipal Code.  The City may also require the applicant to appear before the Planning Commission to address any deficiencies or unapproved modifications.  The project may also be subject to delays in issuance of permits, certificates of occupancy, recordation of plats or other project approvals.
     
  7. Approval of the proposed plat shall be limited to the illustrations and plans presented to the Planning Commission for review and approval on January 3, 2023.  Any changes to Planning Commission approved plans and specifications will require staff review and re-approval by the Planning Commission.
Staff Recommendation
Staff requests that the Planning Commission vote to approve the proposed final plat subject to the requirements of the staff report.
Attachments
Vicinity Map
Proposed Final Plat

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved